2022-04-03
Apr. 3, 2022 - In the sinter shop of the Magnitogorsk Iron and Steel Works (MMK), commissioning work is underway on the updated sintering machine No 12 of sinter plant No 3.
The contract for the supply of sinter machine No 12 of sinter plant No 3 was signed in May 2021. The equipment was manufactured by the enterprises of the UZTM-KARTEX Group’s Uralmashzavod in Yekaterinburg and Uralmash-Mining Equipment in Orsk. On the new sintering machine, the layer of charge was increased, and rippers were also mounted to ensure gas permeability. The launch of the new machine will make it possible to replace outdated equipment, increase the production of sinter, and reduce gas consumption.